screed Christmas
the pouring of the topping scheduled last Friday finally took place today Wednesday because of weather ... it is a screed called "anhydrite" of a thickness of 7 cm, and levels off by itself ... a small broom, and presto, tile glued directly over ... but not before 7 weeks of drying (1 week per centimeter)
start pouring
once reached the desired thickness, the screed is "vibrated" a first After thoroughly to remove air bubbles, then a second time to refine the surface leveling (above)
and here is the result! 47 m2 with tiled ... the formwork on the left is the location of the shower (for those not recognized), deep kitchen sink, and in the foreground, evacuation and feeding the washing machine ... "But-why-he-is-like-it-the-pipe? Bin because the supervisor, he had not been back in the right place ... this one, it will always make us c. ...
if the bales are finite in northern facade (those still in the ceiling above joists), the blades of the ceiling of the ground floor are planed and machined ...
the pouring of the topping scheduled last Friday finally took place today Wednesday because of weather ... it is a screed called "anhydrite" of a thickness of 7 cm, and levels off by itself ... a small broom, and presto, tile glued directly over ... but not before 7 weeks of drying (1 week per centimeter)
start pouring
once reached the desired thickness, the screed is "vibrated" a first After thoroughly to remove air bubbles, then a second time to refine the surface leveling (above)
and here is the result! 47 m2 with tiled ... the formwork on the left is the location of the shower (for those not recognized), deep kitchen sink, and in the foreground, evacuation and feeding the washing machine ... "But-why-he-is-like-it-the-pipe? Bin because the supervisor, he had not been back in the right place ... this one, it will always make us c. ...
if the bales are finite in northern facade (those still in the ceiling above joists), the blades of the ceiling of the ground floor are planed and machined ...
Sunday, December 12, 2010
Lorazepam Mixed With Benadryl
laying cork boards
program of the weekend: laying cork boards
cutting, leveling, plating-with a little sand
brake adjustment steam, so it stays in place when the screed
and formwork (separation between the living room with wooden floors and kitchen with tile)
a little housekeeping ... tomorrow and the carpet ...
program of the weekend: laying cork boards
cutting, leveling, plating-with a little sand
brake adjustment steam, so it stays in place when the screed
and formwork (separation between the living room with wooden floors and kitchen with tile)
a little housekeeping ... tomorrow and the carpet ...
Sunday, December 5, 2010
Beyblades Ina Australian Shops
cow!
Finally, we can begin to interior decorating our future: a beautiful thermometer selected by Naomi! it shows this Friday for a 2 ° outside temperature of -4 °, without doors and the north wall have not yet been isolated, not bad ...
you have another little straw for the north face Friday with Geoffrey and Christian
Saturday with Charlie, and also John the Baptist and Blandina, future builders straw recalibration program the "willy-boot" (graduated with honors) ...
... assembly / disassembly of the scaffolding ...
... and setting up the boots easy and not easy (high walls): graduation with honors "tonic" (ah yes, we see that John has done boxing ...)
Saturday night it only remains to put the boots over the door: ben my little pig, what a weekend!
Sunday afternoon we rest by laying the pipes hot and cold water ... much preparation before the pouring of the topping on 17
big thank you to Geoffrey, Christian, Jean-Baptiste said, "Gascon," Blandine, Charly and Jean Pape (for custody of the 3 little sheep)
Finally, we can begin to interior decorating our future: a beautiful thermometer selected by Naomi! it shows this Friday for a 2 ° outside temperature of -4 °, without doors and the north wall have not yet been isolated, not bad ...
you have another little straw for the north face Friday with Geoffrey and Christian
Saturday with Charlie, and also John the Baptist and Blandina, future builders straw recalibration program the "willy-boot" (graduated with honors) ...
... assembly / disassembly of the scaffolding ...
... and setting up the boots easy and not easy (high walls): graduation with honors "tonic" (ah yes, we see that John has done boxing ...)
Saturday night it only remains to put the boots over the door: ben my little pig, what a weekend!
Sunday afternoon we rest by laying the pipes hot and cold water ... much preparation before the pouring of the topping on 17